ABBEVILLE — Louisiana regulators wrote a letter to SpaceX saying that they were unable to continue processing the company's application for a Coastal Use Permit for their proposed Vermilion Parish development.
"After careful review of your application for a Coastal Use Permit, we have determined that we are unable to continue the processing of the application until we receive the following information," the Louisiana Department of Conservation and Energy wrote in a letter sent to SpaceX on Monday.
The department notes at the end of the letter that staff will resume processing the application when the information is received.
The letter states that the application does not provide enough information for the Office of Permitting and Compliance to complete a review for inconsistencies with the Louisiana Coastal Resources Program. The department cannot continue processing SpaceX's permit application until more information is submitted.
"This thought that it's paused is incorrect; it's not paused. In fact, you know the fact that we've sent them questions indicates to you that we are actively reviewing it, and making sure that everything is included in the application is correct, it provides enough information in order for us to make a decision," Secretary of the Louisiana Department of Conservation and Energy Dustin Davidson said.
The letter also states that if the issues with the application are not fixed within six months of when the letter was sent, the project will be deemed inconsistent with Louisiana's approved Coastal Management Program. It's not immediately clear if there is an appeals process for the permit application to move forward if it is deemed inconsistent.
In its seven-page letter, the Department of Conservation and Energy has asked SpaceX to provide documentation of interagency coordination confirmations with the Louisiana Department of Wildlife and Fisheries and the Coastal Protection and Restoration Authority to protect nearby sensitive features, wetlands and existing shoreline protection projects.
"I will say with any project there's always a concern with impact to wetlands, right, and there is also a concern that they maybe unintentional impacts, right, but what we're really focusing on here is just making sure that what they have on paper is exactly what they've expressed to us verbally," Davidson said
It is also asking for detailed environmental impact and mitigation documentation, including an updated Habitat Impacts Table, site impact analyses for dewatering areas and dredge pipeline corridors, bankline stabilization methods, and a restoration plan to return temporary construction features to pre-existing conditions.
Finally, the state requires extensive engineering revisions across the canal dredging, inland wharf, gulf wharf and roadway permit sets to provide missing cross sections and dimensions, clarify excavation and spoil placement details and resolve numerous discrepancies in elevations, station numbers, acreage totals and map layouts.
"I mean when you're submitting an application for something as significant as an application like this, or even as a small, you know, dock project, fishing pier, or wharf or whatever it may be, most of the time applicants don't get it completely right 100%, so we have to go back to them and say 'hey you have to correct this," Davidson said.
The $100 billion investment—which SpaceX bills as the largest capital investment project in Louisiana history—is expected to begin next year, with the first launch planned for as early as 2029.
When the project was first announced in August, Elon Musk compared it to something that previously "has only existed in science fiction." However, residents of the area have had concerns about the project from the beginning.
In late October, residents of Vermilion Parish filed a lawsuit against the Vermilion Parish Police Jury and Industrial Development Board, accusing the groups of having illegal meetings about SpaceX. The lawsuit alleges eight violations involving government meetings, public notices and decisions tied to SpaceX.
SpaceX, headquartered in Texas, must now address the state's concerns before regulators continue processing the application.